Q2 Risk 5API Spec. Q2 – Online Quiz
Q1 Risk Contingency Planning Quiz
Quiz Summary
0 of 10 questions completed
Questions:
Information
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
Results
Results
0 of 10 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- Current
- Review
- Answered
- Correct
- Incorrect
-
Question 1 of 10
1. Question
At a minimum, contingency planning shall include:
CorrectIncorrect -
Question 2 of 10
2. Question
The output of risk assessment is used in contingency planning.
CorrectIncorrect -
Question 3 of 10
3. Question
Contingency planning may or may not be a required part of the risk assessment process.
CorrectIncorrect -
Question 4 of 10
4. Question
A _________ philosophy is a detailed plan that takes into account the part’s replacement history and shipping lead-time.
CorrectIncorrect -
Question 5 of 10
5. Question
The goal of risk assessment is to eliminate risk.
CorrectIncorrect -
Question 6 of 10
6. Question
Risk assessment should be conducted only by risk auditors. Involving other personnel in the process can result in “group think” that undermines the integrity of the process.
CorrectIncorrect -
Question 7 of 10
7. Question
Risk is defined in the specification as a situation or circumstance that has both a likelihood of occurring and probability of __________ consequence.
CorrectIncorrect -
Question 8 of 10
8. Question
The risk assessment process is a structured way to figure out whether the way you are operating is appropriate, or if there are other things you should or should not be doing that ___________ risks to reasonable levels.
CorrectIncorrect -
Question 9 of 10
9. Question
Contingency Planning and Management of Change are not a part of the Risk Assessment section of Q1 but they are closely related and integral to the risk assessment process.
CorrectIncorrect -
Question 10 of 10
10. Question
This course follows the flow of the risk analysis process. Place the risk assessment steps below in the correct order.
-
Develop management of change plans
-
Rank risks pre-mitigation
-
Identify risks
-
Rank risks post-mitigation
-
Develop contingency plans
-
Develop risk mitigation plans
CorrectIncorrect -